Sample Progress Report (Unit four)
Progress Report
Sample Progress Report
Q. You are Raghvendra Mishra The Assistant Project Manager Satya Prakash Associates Pvt Ltd. Write a progress report on the progress of construction of retaining wall in the catchment area the dam.
Answer.
Satya Prakash Associates Ltd.
Tehri Garhwal (UK)
Interoffice Memo
To: the Project Manager
From: Asst. Project Manager
Reference: PD -034
12 May 2004
Subject: Daily Progress Report (Retaining Wall)
1. Name of the Project: Tehri Dam Project under Satya Prakash Associates
2. Work: Construction of Retaining wall in the Catchment Area
3. Date: 12 May 2004
4. Mixed Concrete used today: 700 cubic meters
5. Mixed Concrete left today: nil
6. Percentage of work completed: 65.33 %
7. Percentage ahead or behind the daily target: 14% ahead the target
8. Remarks if any
c.c. The Managing Director Tehri Garhwal
Signature: Raghwendra Mishra